Thursday, July 23, 2009
Executive Office Building Study – Update 7
The State of Utah has adopted LEED 3.0 Silver or better as it standard for energy efficiency for all new buildings. In compliance with this directive from the State Building Board the study team has analyzed the proposed new 4 story Executive Office Building, as identified in the Workshop, and found that it easily meets or exceeds the requirements of this third party rating system. The master plan update will include an analysis of the other options which will include; 1) Analysis of the existing building and what deficiency would need to be improved in order to upgrade to LEED 3.0 Silver. 2) Review and recommendation for a restoration of the existing building. 3) Analysis of the option exploring an addition to the existing building. All of the Analysis will be include in the Master Plan in order to give future planers the best information available today.
With the understanding gained from the workshop and the economy in the condition it is, it is likely that the Executive Office Building will not proceed forward for at least 5 to 10 years. This poses a major question of how dose the Board keep the existing State Office Building functional while the majority of the systems are approaching failure. In order to address this concern the team lead by the executive director has been working with DFCM’s energy group to study the possibly of employing the capabilities of an ESCO (Energy Service Company) who will help with funding, design and construction. They will also provide a guarantee that the project will hit the projected energy saving. This is critical since it is the savings that are used to pay back the funding commitments. The preliminary analysis shows over 25 different project opportunities. Of those several have a payback cycle of 10 years or less. The plan would be to move forward with the one’s that have a payback which is less than or equal to the length of time estimated before the building is demolished, or approximately 10 years. The master plan will then incorporate this as one of the phases of work identified.
In addition to the projects that will improve the energy efficiency of the State office building there are projects that must be completed to keep the building functional. This will continue as they have in the past with funding from DFCM Improvement funds.
Several other things were identified during the Workshop that needs to be accomplished prior to the demolition of the State Office Building this would include the extension and completion of the fiber loop from the capitol to Rampton and the University of Utah. This extension will allow the removal of the antenna and the communication dishes on top of the State Office Building.
The Architect will develop a complete application set of documents that will be a 3d model for the proposed new structure which will be built during the construction phase of the master plan. This will also include the encapsulation of the Data Processing Center as part of the terrace that is north of the new executive office building. The building shall contain a 300 seat auditorium work space (similar to an airport executive lounge) for the executive staff that is required to be on Capitol Hill during the session. This will be their office space during the session and interim days on the hill. Additionally the building should provide for flex space that can be used by the Governor to move programs on and off Capitol Hill as needed to accomplish the administrations goals. Beyond this the building will be designed as a spec office building, with open floor plates. At the time of design programming will be incorporated to determine the occupants and their needs and will be built out as tenant finish space for the specific office needs. Beyond the building to the east will be a new memorial that will be built at the north end of the site with a small reflecting pool.
The final phase of the Executive office building master plan will be the decision to remove from the hill the Data Processing Center. There is at this time no time estimate as to when or if this decision will be made. It is clear that moving the center will be very expensive and time consuming. However it is important to note that the current location is not the most efficient. There are much better sites that can be found throughout the state that would offer a better over all solution to the needs of DTS. Once the Data Processing Center is moved then the cooling towers would be incorporated into the larger pool element behind the executive office building and the completion of the master plan would be achieved.
The architect is also currently working on a physical model that will be on display in the public lobby of the capitol directly across from the main entry to the gift store. This model will show how the site will look with the completion of the north building and at the completion of the master plan. The model should be complete and ready for installation prior to the end of the 2009.
Friday, May 29, 2009
WORKSHOP – DAY THREE
The most interesting comparison was between option 1c – Restore with a classical skin and the option 3 – New building. This discussion recognized the cost increase from 3 cm stone panels in option 1b to cubic stone elements on the option 1c due to the classical architecture applied to the existing building. What was surprising was the relative closeness in the projected cost of option 3 to that of option 1c. It was also the best comparison of the cost differential between remodeling and building a new building which was approximately 8% increase based upon the provided numbers. This was attributed to the cost of structure and foundations. Yet it was clear that with the new building operational efficiency was increased and the sense of place was preserved.
Option 2 – Remodel and add additional space was the most expensive option of the five that were studied. This had to do with the addition of 150,000 GSF to the existing 171,000 GSF of the current state office building. On top of that it was also the only scheme that would have required additional parking of approximately 150 cars which is a major impact to the site as well as the cost.
After much discussion the unanimous decision that was reached was to proceed from this point only with option 3 – New building. The reasons provided were all focused around three very important concepts which were:
1. Context – the Capitol Preservation Board with the development of the Senate and House buildings and central plaza directly behind the restored capitol has developed a sense of place that no one wanted to see changed. In fact everyone wanted to see this sense of place, the island if you will reinforced. Materials, proportion, height and classical details were all critical to the accomplishment of the context of place. It was felt that using the bones of the existing building would severely limit the ability to maintain and reinforce the sense of place that is so important.
2. Space utilization – the existing building has a narrow floor plate that is very difficult to work around. The need of the modern working environment needs to be flexible to allow for all the demands that are placed upon the state. To maintain a facility that does not provide for the proper use of space limits in the long term the efficiency of the state. It was felt that the money would be better spent providing a more flexible open office environment in a new building than trying to fit functions into a non flexible existing frame.
3. The long view – the group recognized that a new building will be more difficult to fund during the current economic environment that we find ourselves in today. However, they all agreed that it is better to look to the future and to do the right thing for the long view rather than be short sighted and rush to do that which will improve the visual aesthetics of the campus will limit for the long run the usefulness of the building. It was better to build for 100 years than to rush the process. With that said they all want to see the process continue and not lose momentum as the state works through the economic issues.
Based upon this discuss without asking them to review the current CPB master plan they reconfirmed that it should in fact be completed.
During further discussion the workshop group did want to see the north side of the site improved. The concept of the pond and the axial termination was very important to them to retain and complete the context and sense of place that is found on Capitol Hill.
With this recommendation made they suggested that the project definition team continue to study a new building that would contain and achieve the following:
1. Building size – the site caring capacity is limited by parking and land. The group felt that over building was not as important as building the right size for the site, and that maximizing the square footage was less important. The following guidelines were provided that the new building should be no:
a. Longer than that of the capitol in the east west direction.
b. Wider than the base of the capitol in the north south direction
c. Taller than four stories in height above the plaza, in order to act as a backdrop to the plaza and to provide the proper level of containment for the plaza.
2. Classical Design – the group directed the project definition team to study a classical ionic design that would be compatible in material and aesthesis with the campus.
3. Program – must include at a minimum:
a. Flexible open office space
b. 200 to 300 seat auditorium
c. Technology such a video conference rooms
d. Executive Directors office suite/meeting space
e. Parking for Executive Directors
4. Energy Efficiency – conform to the new LEED standards
In addition to these items the workshop group suggested that the executive director begin to develop improvement projects to take care of several critical and important problems associated with the exiting building. These included but were not limited to:
1. Improved energy – study all energy related savings options. Those that have a pay back of 5 to 7 years should be advanced and completed. Projects beyond 10 years should not be considered since the life of the building should not be expected to go beyond that time frame.
2. Electric switch gear – it was discovered in the workshop that the SOB is in need of new switch gear to avoid a failure.
3. Cladding restraint system – the exiting concrete panels on the exterior of the state office building need to be restrained from falling during an earthquake. A simple strap to catch and hold the panel would be advisable.
4. Fire dampers – several life safety issues exist and fire dampers would solve some of those.
5. Microwave antennas – the microwave system needs to have the fiber look completed and the permanent relocation of the north antenna moved to the traffic operations center.
6. DFCM relationship – work closely with DFCM to move organizations off the hill so that relocation costs of rental space are kept to a minimum.
Master plan recommendations were also discussed and included:
1. A shuttle system from the campus to the inter-modal hub in SLC.
2. A van pool from the capitol the Fair Park during session for employees
3. Van Pool and Car Pool reserved parking stalls near entries – encourage more van/car pooling and less individual cars
4. Investigate once again charging employees and public for parking similar to the university.
This was an excellent workshop. A tremendous amount good work came out of it. Many ideas were clearly discussed and resolved. The executive director would like to thank the workshop group made up of private citizens, state employees, members of the preservation and maintenance subcommittee and member of the budget and board operations subcommittee, who all participated openly and shared their ideas. Also to the project definition team member which included architects, engineers and estimates who provide a great amount of information and lead the discussions without a preconceived outcome. Thank you all.
Over the next several weeks the project definition team and the executive director will prepare information that will be presented to the subcommittee and then ultimately to the board for their discussion and approval.
Wednesday, May 27, 2009
WORKSHOP - DAY TWO
1. Restore the Existing Building
a. Historic Skin
b. New Energy efficient Skin
c. New Compatible Skin that uses the design guidelines for new building
2. Remodel existing structure with an addition
a. Three story addition on the south and north
b. Four story addition on the south and north
c. Phase additions to the existing building
3. Demolish and Build a new building
4. Build a new modern building in the hillside using the design guidelines for new building and demolish the existing building.
Each of the options was judged by the workshop team based upon the prioritization of the design guidelines which were voted upon earlier. These include:
1. Materials (78)
2. Energy & sustainability (46)
3. Operational Continuity (41)
4. Subservience (38)
5. Symmetry of Plan (36)
6. Windows (35)
7. Classical Orders (33)
8. Mass & Volume (32)
9. Axis (25)
10. Column (25)
11. Balustrade (24)
12. Symmetry of Elevation (23)
13. Proportion (22)
14. Rhythm (21)
15. Perstyle (19)
16. Floor Alignment (19)
17. Human Scale (14)
Throughout the discussion of each option the working group evaluated the options based upon the prioritized list of design guidelines. At the end of the day the following direction was provided to the design team.
1. Proceed with the following options for future review and discussion
a. For budget purposes only study the restore with new energy effect skin and compatible materials. This is not a preferred option just a base line.
b. Study the application of a historically detailed skin on the existing building without expansion.
c. Expand the existing building with new space located on the north and the south. Expansion may be as large as 150,000 GSF. For every 1,000 GSF of new office space add one parking stall.
d. Demolish the existing building and study the development of a 180,000 GSF new building.
e. Studies the options of a new modern building designed using the guidelines for new buildings but set it back into the north hill, then demolish the existing building.
2. provide cost data
3. Develop a new master plan with whatever options seams to be the preferred after study.
Tuesday, May 26, 2009
WORKSHOP – DAY ONE
During the first day of the workshop on the State Office Building the project definition team provided their findings to the working group. These findings are as follows:
Structural Issues – Summary of Primary Issues
-The original State Office Building was designed in 1959. The design did not deliberately address seismic loading.
-Structural Renovation in the early 1990’s included the addition of significant reinforcement to the existing steel frame.
-Analysis of the retrofitted building indicates that its performance is significantly improved over the original design. However, the expected seismic performance of the steel frame in consideration of a large, rare seismic event is marginal.
-Project seismic drifts are large and will result in significant nonstructural damage and potential instabilities at the lower levels.
-Cladding and cladding attachments will likely fail even for a small quake resulting in cladding falling from the building.
-Building expansion joints do not have sufficient width to prevent pounding across the joints. Seismic motion will cause severe structural damage at the joints.
Mechanical - Summary of Issues:
-Heating and chilled water are provided to the SOB from the new central plant.
-Two chillers are present in the SOB, but are only used when chillers in the central plant are down. These two chillers in the SOB are in excess of 20 years old and use a refrigerant that will be phased out.
-The cooling tower on the roof of the SOB is used when the 2 chillers in the basement are running. Tower is original equipment. Tower fill and basin are worn out, should be replaced.
-Two air handlers located in the basement of the SOB provide air for heating and cooling all floors of the building. Fans are original equipment, and could be replaced by more energy efficient modern fans. Some coils in the units have frozen and have not been replaced.
-Many of the controllers on individual VAV boxes (part of the air system) are more than 20 years old and are failing, need to be replaced.
-Ductwork for air distribution is a combination of old and new ducts. Due to numerous contractors working on the system over the years, it is safe to assume the ducts leak, which results in increased energy consumption.
-Existing duct risers do not appear to be enclosed inside fire rated shafts and are not protected with fire/smoke dampers. System does not appear to comply with latest life/safety code requirements.
Anticipated Usable Life Remaining in the Existing Mechanical Systems:
Component - Age - Anticipated Remaining Life
-Heating Water Pumps - New- 35 years
-Chilled Water Pumps - New - 35 years
-Chillers -20+ years - 20 years in stand-by mode (1)
-Variable Frequency Drives - New - 20 years
-VAV Box Controllers - 19 to 23 years - None
-Air Handler Fans - 50 years -Indefinite (2)
(1) Compressors were recently rebuilt, but chillers use a refrigerant that is scheduled for phase-out in the near future, do not have the same controls options found on the new chillers in the central plant, and are not as efficient as modern chillers.
(2) Fan bearings may require replacement over the years. Older fans not as efficient as modern units.
Electrical: Power, Lighting, Fire Alarm and Voice/Data Cabling - Summary of Issues
-The 15 kV switchgear and distribution feeding the building is old, original equipment and is beyond its useful life. It is radial-fed (without redundant paths) from the central plant and is a high-risk single-point of failure for the building. This switchgear and distribution should be replaced with new on a looped distribution system. In addition, the transformers for the building should be replaced based on age.
-The electrical distribution system in the building has been partially replaced and added to over the years. While some of the equipment is new, it was not originally designed to accommodate modern office needs. Many of the electrical panels and rooms are filled to capacity with little room for growth and flexibility. The building electrical distribution system should be replaced in its entirety with new, and located in new, stacked electrical closets.
-Most branch wiring is required to be replaced due to the remodeling that will occur. Problems associated with grounding and power quality have also been reported, which should be corrected with the new branch wiring.
-Lighting is predominantly fluorescent. Many of the fixtures still use T12 lamps with magnetic ballasts. About 1/2 of the fixtures have been retrofitted or provided new with T8 lamps and electronic ballasts. More energy efficient lighting systems are available today and an overall lighting replacement is recommended to improve efficiency. Lighting controls will also be enhanced and added to reduce energy consumption.
-Emergency and standby power will be added to meet current code requirements. Communications rooms and associated cooling will also be added to the generator system to back up the critical data operations in the building.
-Ideally, the fire alarm system should be replaced with a new system so that the building can be consistent with the other buildings and integrated into the computerized graphical annunciation software.
-Telecommunications rooms are overheated and too small to meet current codes and standards. Much of the telecommunications cabling is the older standard CAT 3 and CAT 5 cabling that will not support higher speeds that the new CAT 6 standard will support. New telecommunications closets and cabling is required to bring the building up to current standards and provide a more reliable, high-speed network.
Wireless Wan Communications - Summary of Issues:
-The state communications network consists of an extensive microwave system plus a fiber optic network. These two systems provide the redundancy necessary for the critical operations of the state communications needs.
-If the State Office Building is removed, the antennas for the microwave network located on the roof plus the electronic equipment located in the penthouse will need to be relocated. The traffic on this system will need to be maintained and remain in service during the construction phase. The recommendations below permanently relocates the microwave equipment to other locations and would not require moving that equipment back to the new State Office Building.
Three backbone microwave paths are presently in service
· One to the Ogden area via Ensign Peak
· One to the University of Utah
· One to the Technical Operations Center
Two spur microwave paths are presently in service
· One to the BLM
· One to the FBI
Additional communications systems
· Several communications systems for Homeland Security
· At least two cellular telephone companies (the cell companies are responsible to relocate to other facilities if required by the state)
A DACS is located in the penthouse and is used for grooming T1 traffic
Recommendations:
-Install a fiber optic loop with new fiber installed in existing UDOT conduit between the Cal Rampton building and a splice location near Highland Drive.
-Obtain use of fibers in an existing cable owned by the university between ECCLES and the splice location near Highland Drive.
-Relocate the Ensign Peak microwave equipment form SOB to either ECCLES or TOC.
-Relocate the FBI and BLM microwave equipment to alternate locations.
-Relocate the Homeland Security equipment to an alternate location.
-Relocate the DACS equipment to the data center.
Executive Office Building Study – Update 6
The structural report went on to identify that building during a significant earthquake of expected magnitude (7.3) would sway approximately 20” in both directions. While the building would not collapse two major problems would occur:
1. The building would attempt to tear its self apart at the expansion joint in the center of the building. This is due to it heavy core and light frame. The earthquake would cause a swaying motion at the extreme east and west ends of the building and the osculation would force the building into a sin wave with the neutral point at the expansion joint. This would result in tearing at the expansion joint which if a larger quake was to hit the building could possibly result in portion of the building collapsing.
2. The exterior skin of the building can not withstand the movement of the building during a significant event. The concrete panels and the aluminum windows would completely disconnect from the building would either be dropped to the ground in the case of the lower elements or flung from the building in the case of the upper panels. This is due largely to the way the connections are made and the material used in the connection as well as the tolerance that was designed into the system when it was build which is very limited. The only remedy for this situation is to completely remove the exterior skin and replace it with a design that provides for a more robust connection and a exterior enclosure that would allow for greater movement during a seismic event.
The mechanical and electrical reports were not available at the time of the meeting however, the project definition architect explained that the mechanical systems and the electrical systems are no longer able to meet the needs of the occupants. That it will be the teams recommendations that the two systems are completely replaced with modern state of the art systems. This will provide greater energy efficiency which will reduce energy costs and will provide a better overall working environment for the occupants.
The workshop where all the different options will be reviewed is scheduled for May 26, 27 and 28. Invitations are being sent out to members of the board and other interested individuals.
The workshop format will as follows:
Day One-Discovery – May 26 from 10:00 AM to 2:00 PM
• Presentation-Options
• Values/Drivers/Idea Hierarchy-Care the most about
Day Two- Open House/Larger group input – May 27, 10:00 AM to 2:00 PM
• Present ideas/Options to larger groups and listen for input
• Adjustment in idea Hierarchy based on larger group
Day Three- Resolution – May 28, from 10:00 AM to 2:00 PM
• Working Session - Morning
• Summary of Values and Idea Hierarchy
• Development of concept refinement
• Consensus- Summary
• Agreement for direction of future work effort
Following the workshop a synopsis will be developed and distributed both on the blog and to board members.
Tuesday, April 21, 2009
Recession Means Bargains for Government
"The economic downturn is wreaking havoc on state and local government budgets. But amid the gloom there is a bright spot: construction costs.
During the past nine months, the state of North Carolina, Raleigh, Durham, Wake County and other local governments have seen all types of construction projects coming in under budget, some by as much as 30 percent. But the friendliest building climate in years is coming when many private and public entities have little or no money."
For more about this artical click here
Monday, April 13, 2009
Executive Office Building Study - Update 5
The facilities assessment of the State Office Building is complete. The findings of the structural, mechanical and communication systems are being reviewed and recommendations will be provided on how to proceed.
A workshop is scheduled for May 26, 27 and 28, 2009 to review the following three options of the State Office Building:
Option 1 - Restore the Building - The following will be discussed:
· Historic significance
· Cost/value of restoration and seismic upgrade
· Occupants/lease/move/cost
· Floor heights/plaza
Option 2 – Remodel/Renovate – The following will be discussed:
· Building additions on north and south sides
· Impact to data processing
· Site access and constructability
· Energy efficiency
· Occupants
· Floor heights
· New skin with same look/additional square footage - Add up to 150,000 GSF and Better materials/granite/ HP glass/insulation
· New skin with new look (LEED silver) - Add up to 150,000 GSF and Granite/ HP glass/Marriott Library Federal Building
· New skin with classical look - Add up to 150,000 GSF, Granite/punched openings/classical details and Granite–match Senate and House buildings
Option 3 - Replace Building - The following will be discussed:
· Impact of data processing
· Communication antennas
· Site access and constructability
· Occupants
The schedule for the workshop is as follows:
May 26, 2009 - Discovery
· Present options
· Values/drivers/idea hierarchy (care the most about)
May 27, 2009 - Open House/Larger Group Input
· Present options to larger groups and obtain input
· Adjustment in idea hierarchy based on larger group
May 28, 2009 - Resolution
· Working session
· Summary of values and idea hierarchy
· Development of concept refinement
· Consensus/summary
· Direction of future work effort
Thursday, March 26, 2009
Executive Office Building Study – Update 4
Paul D. Brown, AIA has been studying option two (add to the State Office Building) and three (remove the existing building and build a new structure). These studies will provide information to the Board members and members of the team who will hold a workshop on May 26, 27 and 28, 2009 to review the options and provide direction to the executive director and consultants.
During April, the executive director and consultants will speak with many executive branch leaders around the Salt Lake Valley to understand their interaction with agencies on Capitol Hill. Interviews will also be conducted with occupants of the State Office Building to determine their needs. This information will help determine the programming and space planning of the State Office Building and will be presented to the Board. This information will also be presented during the workshop in May.
Wednesday, March 11, 2009
Executive Office Building Study – Update 3
The information provided for the mechanical and electrical was consistent with the preliminary information as was stated in update - 1.
Structurally the building had received several seismic upgrades which have strengthened the building over that which was initially believed. The strengthening has taken place in the east west direction which was already the strongest direction and has not added much to the north south where the greatest concern is. There are some mitigation techniques that can be applied to the structural framework that can save the building, but the cost is questionable due to its expense.
The communication system that is atop of the State Office Building has been of great concern. With the evaluation complete the report from the consultant has identified several issues which is most critical to the state and it continued operational needs. These include:
· Communication systems must be kept in service during any renovation.
· Fiber is currently in place and may be used to relocate traffic from the microwaves during the renovation is permission for use can be obtained?
· There may be need for new locations, alternative sites and pathways during the renovation or remodeling for all needs. Costs will be an issue.
· Cellular telephone would be interrupted during the restoration.
· Before any work can begin multiple agencies will need to be coordinated with to make sure their needs are not overlooked.
Additionally the project definition consultant and the executive director discussed the May 26, 27 and 28 workshop. It is anticipated that during the workshop participants will be asked during the first day to assimilate the data gathered to date. They will also review the guidelines and imperatives for new buildings on Capitol Hill. They will then discuss which guideline and which imperative is critical to maintain as we move forward with the development of guidelines for existing or remodeled buildings on Capitol Hill.
Day two and three the workshop will focus upon the conceptual direction the project may go. Options will be discussed and participants raise issues and questions. The goals of the workshop will be to:
· Provide clear direction on options for the Board to review
· Determine facility fitness and what should be placed on the site.
· Identify the important elements that they care the most about to be incorporated into the options.
Monday, March 9, 2009
Executive Office Building Study – Update 2
1. Restore the existing State Office Building to the 1959 design
2. Retain the building structure (with modifications) and re-skin the building with a more compatible design for Capitol Hill and its master plan.
3. Retain the building structure (with modifications) add on to the building to increase square footage by adding space to the north, south or both.
4. Remove the existing building and design a new structure that is compatible with Capitol Hill and it master plan.
There are several constraints that the consultants and the executive director will have to address in the study and analysis of each option these include:
1. Displacement of occupants of the existing State Office Building.
2. Parking on Capitol Hill.
3. The State of Utah is currently in need of some 150,000 GSF of space in Salt Lake Valley.
4. Communication equipment located on top of the State Office Building.
5. Data Processing Center located behind the State Office Building.
6. Accessibility to the facilities during construction.
7. Height relationships.
8. Energy Efficiency and environmental sustainability.
9. Functional needs on Capitol Hill.
10. Agency needs on Capitol Hill and off.
The executive director and consultant have identified May 26, 27 and 28 of 2009 as a workshop where members of the Board, employee and community member will be invited to participate and share their thoughts and ideas for the Executive Office Building.
Executive Office Building Study – Update 1
· Structural System is inadequate for the seismic conditions of the site and will not survive the predicted seismic event for Capitol Hill. This is due largely to the minimal size of columns and other structural elements in the building.
· Mechanical Systems are old and antiquated. Many of which have been held together with good maintenance procedures but have outlived their useful life by many years. Systems are now in a state of progressive failure and are predicted to become more troublesome with each passing year.
· Electrical and Data systems have been overlaid many times in the 50 years the building has been in service. While wire management has been employed there is still a variety of problems and incompatibilities that exist within the systems.
· Architecturally the building space plan is inefficient due to it size and shape reducing the office area to long single loaded office environments or large open spaces suits that are both over crowed and underutilized.
A complete report will be published at the conclusion of the assessment phase of the work.